DHL, South Shields: 366 kWp warehouse installation

804 panels on a trapezoidal warehouse roof, won at competitive tender, cutting energy costs and carbon for one of the world's biggest logistics operators.

Drone view of the 366kWp solar array on the DHL warehouse in South Shields
System size
366 kWp
JA Solar modules
804 x 455W
High-performance inverters
6
Grid control board
G99
Energy monitoring
Live
Commissioned
April 2025

In April 2025, Green Team Partnership secured a competitive tender to deliver a 366 kWp commercial solar system at a major warehouse site in South Shields. With DHL set to occupy the building, the installation significantly reduces operational energy costs and carbon output from day one of occupation.

The system carries 804 JA Solar 455W modules, mounted on a trapezoidal roof using specialist equipment for maximum efficiency, with six high-performance inverters, a G99 control board and real-time energy monitoring giving full visibility of generation and savings.

Impact and benefits

  • Serious generation capacity. 366 kWp of clean electricity lowers annual grid dependency and shields the tenant from rising energy prices.
  • ESG alignment. The project contributes directly to DHL’s carbon-reduction commitments and environmental reporting.
  • Enhanced property value. Better energy performance strengthens the site’s rating, which matters to commercial investors and tenants alike.
  • Low-maintenance design. Quality components and professional installation keep the system producing for decades.
  • Full transparency. Live monitoring lets site managers track output and system health continuously.

On site at DHL

Tap any photo to see it full size.

1 / 4

The full 366 kWp array across the DHL warehouse roof in South Shields
The full 366 kWp array across the DHL warehouse roof in South Shields
JA Solar 455W modules mounted on the trapezoidal warehouse roof
JA Solar 455W modules mounted on the trapezoidal warehouse roof
Overhead view of the panel rows running the length of the DHL warehouse roof
Overhead view of the panel rows running the length of the DHL warehouse roof
Six high-performance inverters and the G99 control board installed at the DHL site
Six high-performance inverters and the G99 control board installed at the DHL site

More installations